At Infranium Homes, we believe in transparency, consistency, and keeping our community informed at every stage of development. We're excited to share the construction progress of our premium project – Vvie Villas, a collection of luxury villas nestled in the iconic naldehra golf hills shimla.
📍 Project Timeline So Far
🔹 December 2024 Site development officially kicked off.

🔹 January 2025
Foundation work began for Villa No. 5 & 6.

🔹 February 2025
Column work completed for Villa No. 5 & 6.

🔹 March 2025
Slab work executed for Villa No. 5 & 6.

🔹 April 2025
Second floor slab and roof work completed for Villa No. 5 & 6.

🔹 May 2025
Superstructure completed for Villa No. 5 & 6.

Foundation work for Villa No. 3 & 4 commenced.
🔹 June 2025
Structure of Villas 5 & 6 and ground floor of Villas 3 & 4 completed.

🔹 June End
Plaster work & Roof Work of Villa No. 5 & 6 Completed


🔹 July 2025
Second floor Slab For Villa No. 3 & 4.


🔹 July 2025
Site Office Near Completion.

🔹 Aug 2025
MEP of Villa 6 & 5.

🔹 Aug End
Structure of Villa 4 & 3 near Completion.

🔹 Aug 2025
Structure of 4 villas completed

🔹 Aug 2025 End
Foundation Work for Villas 2 & 1

🔹 Sept 2025
Plaster Work for Villas 6&5

🔹 Sept 2025 End
Exterior Plaster Work for Villas 4&3

🔹 Sept 2025
Slab Work for Villa 1

🔹 Sept 2025
Foundation Work for Villas 2

🔹 Sept 2025
Electric and Plumbing for Villas 6,5 & 4


Villas Coming to Life